Alan Uren
Project Delays with Better Project Scheduling: How Project Schedule management saved Transocean $24 million
Avoiding Project Delays: How We Saved Transocean $24m & 48 Days
Introduction to Project Scheduling in Complex Construction Projects
In the world of large-scale construction projects, avoiding project delays is a critical yet challenging aspect of project scheduling. The Deepwater Titan project, a massive undertaking by Transocean, serves as a prime example of how effective project scheduling and pull planning can overcome significant obstacles and ensure timely project completion.
The Project Plan and Initial Timeline
The project manager, John McCann, was tasked with overseeing the construction of the Deepwater Titan, a state-of-the-art drilling vessel. The initial project plan outlined an ambitious timeline for completion, with a carefully crafted project schedule detailing each phase of construction. However, as with many complex projects, unexpected challenges would soon test the team's ability to avoid delays and keep the project on track.
Unexpected Changes and Potential Setbacks
As the project progressed, two major changes in project scope threatened to cause significant delays:
Upgrading the mud systems: This required access to the mud room on deck 3, which was already installed.
Installation of a new Managed Pressure Drilling (MPD) system: This necessitated additional piping and a new manifold.
These changes in project requirements could have easily led to delays, potentially resulting in delayed project completion and substantial cost overruns. The project team recognized that poor planning at this stage could lead to a domino effect of setbacks throughout the project lifecycle and began to formulate a project schedule to combat this.
Identifying Common Causes of Project Delays
To address these challenges effectively, McCann and his team first needed to understand the common causes of project delays. They identified several factors that often result in delays:
Inadequate risk assessment
Poor communication among team members and stakeholders
Unrealistic timelines
Scope creep
Resource allocation issues
Unforeseen technical challenges
Recognizing these potential pitfalls allowed the team to develop strategies to prevent delays and keep the project schedule on schedule.
Implementing Robust Project Management Strategies
To overcome the project delays caused by the scope changes, McCann engaged Wayne Greenwood of OverVue Planning Systems Inc. as a project scheduling professional. W Together, they implemented a series of robust project scheduling strategies, using Pull Planning Techniques:
1. Comprehensive Schedule Revision
The team utilized OverVue, our advanced project scheduling and management tool, to revise the remaining project schedule. This allowed them to:
Import the remaining portion of the delivery schedule from Primavera P6
Transform the original Gantt chart into a Project Flow Diagram
Implement unique Spatial Scheduling capabilities
2. Stakeholder Engagement and Communication
Recognizing that effective communication is crucial to project success, McCann initiated information sessions with key project stakeholders. These sessions aimed to:
Discuss the impact of scope changes
Gather input on potential solutions
Ensure alignment on project goals and timelines
3. Risk Assessment and Mitigation
The team conducted a thorough risk assessment to identify potential delays and develop mitigation strategies. This involved:
Analyzing each aspect of the project for potential risks
Developing contingency plans for high-risk areas
Allocating resources to address identified risks proactively
4. Dynamic Project Tracking and Monitoring
To keep the project on track, the team implemented dynamic tracking methods:
Real-time updating of the project schedule using OverVue’s pending project scheduling software
Weekly review sessions to assess project milestones
Overcoming Construction Delays
Thanks to OverVue and their new project scheduling tools in place, the team tackled the construction delays head-on. They focused on several key areas:
Mud System Upgrade
To address the challenge of upgrading the mud system, the team:
Developed a detailed access plan for the mud room
Coordinated with equipment manufacturers to minimize downtime
Utilized off-hours work schedules to accelerate the upgrade process
MPD System Installation
For the new MPD system installation, the team:
Collaborated with Houston-based manufacturers to expedite production
Prepared the installation site in advance to minimize on-site work
Utilized parallel work streams to install piping while awaiting the manifold
Results and Project Success
The implementation of these robust project scheduling strategies yielded impressive results:
Reduction in revision estimate by 48 days
Cost savings of $24 million USD
Schedule revision completed in just 5 days
These outcomes demonstrated the team's ability to manage project delays effectively and bring the project back on track.
Lessons Learned and Best Practices
The Deepwater Titan project provided valuable insights into avoiding delays in construction projects:
Proactive Risk Management: Anticipate and plan for potential setbacks before they occur.
Flexible Planning: Be prepared to adjust the project plan and timeline as circumstances change.
Stakeholder Engagement: Keep all project stakeholders informed and involved throughout the project.
Utilize Advanced Tools: Leverage project scheduling software to enhance decision-making and tracking.
Continuous Improvement: Regularly review your project's progress and adjust strategies as needed.
The Importance of Quality in Project Deliverables
Throughout the project, the team remained focused on maintaining the quality of project deliverables. They recognized that rushing to meet deadlines could compromise the overall quality of the work. To prevent this, they:
Implemented rigorous quality control measures
Conducted regular inspections of completed work
Ensured that all project requirements were met or exceeded
Communicating Project Delays and Progress
One of the key factors in the project's success was the team's approach to communicating project delays and progress. They:
Provided regular updates to all stakeholders
Were transparent about challenges and setbacks
Celebrated milestones and successes to maintain team morale
Conclusion: Overcome Project Delays
The Deepwater Titan project demonstrates that even in the face of significant challenges, effective project scheduling can help avoid delays and ensure timely project completion. By creating a project schedule, maintaining clear communication, and leveraging advanced project scheduling tools, project teams can overcome obstacles and deliver successful outcomes.
As construction projects and the project scheduling process become increasingly complex, the lessons learned from the Deepwater Titan serve as a valuable guide for project managers seeking to improve the quality of their projects and avoid costly delays. By focusing on proactive planning, stakeholder engagement, and agile management techniques, teams can navigate the challenges of modern construction projects and achieve remarkable results.
Transocean's Deepwater Titan arrived on the day scheduled in the revised project timeline, ready to assist in the offshore drilling operations. The team eagerly awaited its arrival, as it marked a significant milestone in the project's progress.
To learn more about our pull planning and scheduling services, contact us today!